Summary of work experience

Summary of work experience

1. EPC of OBIAFU/OBRIKOM to OBEN (OB2) Gas transmission Pipeline system LOT B (67 km x 52-inch)

CLIENT & LOCATION

Total Energies EP Company Limited, Rivers State Nigeria

WORK SCOPE:

  • Construction, installation and commissioning of OBIAFU/OBRIKOM to OBEN (OB3) Gas transmission Pipeline system LOT B (67km x 52-inch) from the Intermediate Pigging station (around KP 63.45) in Warri
  • Complete Engineering Design of the entire Gas transmission pipeline system LOT A & LOT B (130km x 48-inch)
  • Design and Construction of the Gas treatment Plant, Launcher and Receiver Stations
  • Installation of the Line Break Valves
  • Cathodic protection system
  • Major and Minor River crossings
  • Major and Minor Road crossings
  • Railway crossing
  • Associated Earth and Civil works
  • Electrical/Instrumentation works
  • Telecommunication works
  • Testing and commissioning
2. Fabrication of Scrubber & Mechanical Installation of Gaslift Manifolds and Piping System.

CLIENT & LOCATION

NLNG (BONNY) Natural Gas Plant

WORK SCOPE:

  • Fabrication of Scrubber & Mechanical Installation of Gaslift Manifolds and Piping System

3. Structural & Concrete works for QU0 16 LACT Unit and In – field Dehydration Unit installation project.

CLIENT & LOCATION

Total Energies EP Company Limited, Rivers State

WORK SCOPE:

  • This project entails the provision and installation of steel driven Pipe piles for the support of LACT UNIT Offshore Platform structures. The project belongs toTotal E&P Company Limited.
4. EPRS of a Gas Pipeline.

CLIENT & LOCATION

Addaxx Petroleum (Calabar, Cross Rivers State) Nigeria

WORK SCOPE:

  • Mobilizing of resources

Carrying out construction and hooking up (sectional replacement) of 24-inch x 250m Manifold by-pass line

5. 128 km × 20-inch Gas Transmission Pipeline System – Akwa Ibom to Cross River

CLIENT & LOCATION:

ExxonMobil Nigeria (Mobil Producing Nigeria Unlimited)

WORK SCOPE:

  • Construction, installation, and commissioning of a 128 km × 20-inch natural gas pipeline.
  • Right of Way (R.O.W.) survey, clearing, and preparation.
  • Excavation, trenching, welding, and pipeline laying.
  • Non-Destructive Testing (NDT) for weld integrity.
  • Coating and cathodic protection for corrosion prevention.
  • Flushing, hydrotesting, drying, and nitrogen purging of the gas pipeline.
  • Civil & Infrastructure Works:
    • River crossings (ranging from 1.3 km to 800 m wide).
    • Major and minor road crossings.
    • Swamp and creek crossings.
    • Rocky and hilly terrain construction.
  • Pipeline Facilities & Components:
    • Pressure Regulating & Metering System (PRMS).
    • Line Break Valves (LBVs) for pressure control.
    • Isolation and Protection Systems (IPS).
  • Electrical, Instrumentation, and Telecommunication Installations.
  • Final testing and commissioning for full operation.
6. EPC of 35 km × 16-inch Gas Transmission Pipeline System, Including Gas Metering & Pigging Station Facilities

CLIENT & LOCATION:

 Seplat Energy PlC (Sapele, Delta State, Nigeria)

WORK SCOPE:

  • Engineering, Procurement, Construction (EPC), and Commissioning of a 35 km × 16-inch natural gas pipeline system.
  • Front-End Engineering Design (FEED) for the pipeline infrastructure.
  • Right of Way (R.O.W.) survey, clearing, and preparation.
  • Excavation, trenching, welding, and pipeline laying.
  • Non-Destructive Testing (NDT) of welds to ensure quality and safety.
  • Application of field joint coating for corrosion protection.
  • Flushing, hydrotesting, drying, and nitrogen purging of the gas pipeline.
  • Associated Civil & Structural Works:
    • Foundation construction for metering and pigging stations.
    • Earthworks and pipeline support structures.
  • Pipeline Infrastructure & Facilities:
    • Installation of Gas Metering Station for flow measurement.
    • Construction of Pigging Station Facilities for maintenance operations.
  • Electrical, Instrumentation & Cathodic Protection:
    • Installation of Cathodic Protection System (CPS) to prevent pipeline corrosion.
    • Instrumentation and control system integration.
  • Hot Tapping Works for pipeline tie-ins.
  • Final Testing & Commissioning to ensure operational readiness.
7. Relocation of 750m × 16-inch Gas Pipeline System

CLIENT & LOCATION:

 Indorama Eleme Petrochemicals Limited Eleme, Rivers State, Nigeria

WORK SCOPE:

  • Detailed Engineering Design, Procurement, and Construction of a 750m × 16-inch gas pipeline crossing a river.
  • Right of Way (R.O.W.) Survey and site preparation.
  • Dredging & Excavation for pipeline installation.
  • Pipeline Installation Activities:
    • Trenching, welding, and laying of the pipeline.
    • Non-Destructive Testing (NDT) of welded joints for quality assurance.
    • Application of Field Joint Coating (FJC) for corrosion protection.
    • Cathodic Protection (CP) to prevent pipeline degradation.
    • Flushing, hydrotesting, and pigging of the pipeline.
    • Drying and nitrogen purging to remove contaminants.
    • Final commissioning and integration into the existing network.
8. Supply and integration of data fusion technology and Rental of Injection Skid & Metering Pump for Offshore Operations.

CLIENT & LOCATION:

Chevron Nigeria Limited (Offshore) Nigeria

WORK SCOPE

  • offshore security enhancement.
  • inspection and assessment of Infrared (IR) Compressor to ensure operational efficiency.
  • Leasing of Milton Roy Chemical Injection Skid and Electronic Metering Pump with a storage tank.

Deployment for Chevron’s Offshore Production Facilities.

9. Provision of Completion Fluids & Engineering Services for Workover Operations

CLIENT & LOCATION:

TotalEnergies EP Nigeria (Delta State), Nigeria

WORK SCOPE:

  • Supply of completion fluids for well intervention and workover operations.
  • Engineering support services to optimize well productivity.
  • Filtration and quality control of completion fluids to maintain well integrity.
  • Brine preparation and density control for optimal wellbore conditions.
  • Wellbore cleanout operations before recompletion.
  • Pump and circulation services for downhole operations.
  • Fluid loss control to enhance well performance.
  • Provision of specialized additives for fluid enhancement.
  • Environmental management and disposal of used fluids per regulatory standards.

Testing, monitoring, and reporting of fluid performance throughout operations.

10. Deployment of Supply Vessels for Drilling, Completion & Intervention Support Operations

CLIENT & LOCATION

ExxonMobil Nigeria (Mobil Producing Nigeria Unlimited) Offshore Ondo State, Nigeria

 WORK SCOPE:

  • Provision of supply vessels for deepwater drilling and well intervention support.
  • Logistics and marine transportation of equipment, personnel, and materials to offshore platforms.
  • Dynamic positioning (DP) vessel operations for enhanced station-keeping during offshore activities.
  • Standby emergency response vessels for oil spill management and offshore safety compliance.
  • Anchor handling and towing services for rig mobilization and positioning.
  • Offshore bunkering and refuelling operations to support continuous drilling activities.
  • ROV deployment and subsea intervention support for wellhead maintenance.
  • Deck cargo handling and storage for critical offshore components.
  • Inspection, maintenance, and repair (IMR) support for offshore assets.

Environmental monitoring and regulatory compliance for marine logistics.

11. Development Drilling Operations for Deepwater & Swamp Fields

CLIENT AND LOCATION:

Oriental Energy Resources, Offshore, Madu & Ebok Fields, Akwa Ibom State

WORK SCOPE

  • Execution of development drilling programs to increase production output.
  • Well intervention and workover services to optimize well productivity.
  • Casing and cementing services for offshore completions.
  • Installation of production packers and sand control systems.
  • Deployment of riser less drilling fluids for subsea well completions
12. Environmental Impact Assessment (EIA) & Regulatory Compliance

CLIENT AND LOCATON

Brass Energy, Offshore & Onshore, Bayelsa State

 WORK SCOPE

  • Environmental baseline studies and risk mitigation strategies for offshore and onshore projects.
  • Marine biodiversity impact assessments for offshore drilling projects.
  • Regulatory compliance reporting and stakeholder engagement.
  • EIA studies for additional well drilling and field expansion projects.
13. Offshore Well Stimulation & Production Enhancement Support

CLIENT AND LOCATION:

Ibom Power Plant, Akwa Ibom State

WORK SCOPE

  • Deployment of acidizing and fracturing fluids for production enhancement.
  • Chemical injection and enhanced oil recovery (EOR) solutions.
  • Pipeline pigging and subsea intervention operations.
  • Well monitoring and real-time performance optimization.